Flintshire LDP Delayed – Again

Flintshire LDP Delayed – Again

(July 2020)

Flintshire County Council has received agreement from the Wesh Government to delay the submision of their LDP by 3 months, until October 2020‘as a result of the consequences of the Covid 19 Emergency’.

This is the 4th deferral since the original Timetable (called a Delivery Agreement) was approved by the Welsh Government on 12 February 2014 – when it pointed to the need for a new LDP to be in place ASAP as the existing UDP expired in 2015.

This further 3 month delay means that the earliest the (2015-2030) LDP can be formally adopted by FCC is November 2021!

Click the link below for the latest Delivery Agreement details:
https://www.flintshire.gov.uk/en/PDFFiles/Planning/Flintshire-LDP-Delivery-Agreement-4th-Revision.pdf